A Plan Without a Stop List Is a Wish List

Key takeaways

  • Most banks rank their strategic initiatives but rarely build a Stop List, so every project competes for the same limited people. A Stop List is the set of initiatives leadership explicitly agrees to stop or defer to make room for new work.
  • Before approving any new 2027 initiative, ask what it will replace. If no one can say, the portfolio is overcommitted.

In planning sessions this season, I’ve been putting the same question to bank leadership teams. If you take on this project, what are you willing to stop, delay, or do differently to make room for it?

The most common answer is “nothing.”

At one $50 billion regional bank, leadership wanted to add a major new project to a portfolio that was already full. When we asked what they would remove to make room, they couldn’t name a single project.

That doesn’t mean the team was undisciplined or short on ideas. Most banks have far more good ideas than they can deliver. The problem is capacity, and most planning processes don’t account for it.

Why do bank strategic plans get overloaded?

Look at almost any bank’s 2027 plan right now and you’ll find the same goals. Grow deposits. Cut costs. Modernize the core. Do something with AI. Tighten risk management, improve the customer experience, and stay ahead of new regulations.

On their own, none of these goals is unreasonable. But almost all of them land on the same people. The data team gets pulled into every one. So do risk and compliance, IT, and the business leaders who have to make the change stick. Most banks have lived through what happens next. Projects pile up, teams get stretched, deadlines slide, and costs climb, and by the end of the year it’s hard to say whether any of it moved the strategy forward.

Why ranking projects doesn’t reduce the workload

Most banks do set priorities. Every project gets a number, and the list gets put in order. But putting a list in order doesn’t make it any shorter. The top project gets funded, and so does the one ranked 38th. It just gets in line behind the others.

That’s the core problem. When everything is treated as important, nothing gets the resources it needs to succeed.

What is a Stop List?

A Stop List is the set of initiatives a bank’s leadership has explicitly agreed to stop or defer to make room for new commitments. It turns prioritization into an actual choice: every new project comes with a decision about what gives way. Without a Stop List, you don’t have a plan. You have a wish list.

We’ve seen what happens when a bank actually does this. The operations division of a multinational bank we worked with had 74 strategic projects running at once. After building a formal Stop List, they stopped or pushed back 16 of them, about a fifth of the portfolio. That freed up roughly 15% of the capacity their delivery teams had been stretched across.

What’s the difference between a project list and a strategic portfolio?

Most banks can tell you what’s on their project list. Fewer can tell you why each project is there, what they gave up to fund it, or what it’s supposed to deliver. That’s the difference between a list and a portfolio.

Picture a bank with 40 projects on its annual list. A portfolio view would group them by strategic objective, separate required work from discretionary work, and show the people and money each one needs and where they conflict. You could then see that approving Project A means delaying Projects B and C, or that you’d need more resources before approving any of them.

The structure varies. Some banks run a central enterprise portfolio. Others let business units set their own priorities. Either way, the bank should be able to answer four questions:

  1. What matters most?
  2. What can we realistically deliver?
  3. What should we stop or defer?
  4. How will we know the investment delivered value?

Eight questions to ask before approving a bank initiative

Before an initiative enters the portfolio, leadership should be able to answer:

  1. Strategic alignment: Which strategic objective does it support?
  2. Business value: What will it improve: revenue, cost, risk, customer experience, operations, or compliance?
  3. Urgency: What happens if we wait six or twelve months?
  4. Investment: What people, technology, and capital does it require?
  5. Capacity: Do we have the people and skills to deliver it?
  6. Dependencies: What has to happen first?
  7. Measurement: How will we know it worked?
  8. Trade-off: What will we stop or defer to make room for it?

Most processes skip the last question, but it’s the one that gives the other seven their weight. If an initiative can’t answer it, it may not be ready for the portfolio.

Start before the 2027 budget locks

Fall planning isn’t just about picking next year’s projects. It’s when the bank decides what it can realistically deliver. Once the budget is set, most of those decisions are already made.

So before you lock in your 2027 plan, try this: for every new project you’re considering, write down what it will replace. If you can’t name anything, your portfolio may need a rethink.

Frequently asked questions

What is a Stop List in bank strategic planning?

A Stop List is the set of initiatives leadership has explicitly agreed to stop or defer to free up capacity for new work. It makes sure every new project approval comes with a matching decision about what gives way.

Why isn’t ranking projects enough?
How much capacity can a Stop List free up?
When should a bank build its Stop List?
Which banks benefit most from portfolio discipline?

About the author
Jim Kaminski is Practice Lead for Banking & Operational Excellence at Newbold Advisors. He has spent more than 25+ years leading and advising banks through transformation, at BNY Mellon, JPMorgan Chase, Wells Fargo, PNC, Huntington, Bank One, and Accenture. Learn more about the Banking & Operational Excellence practice.